ACG Partners Greenlight $6B Caspian Sea Development

The Steering Committee for the development of the Azeri and Chirag fields and the Deep Water portion of the Gunashli (ACG) field has sanctioned the Azeri Central East (ACE) project, the next stage of development of the giant ACG field in the Azerbaijan sector of the Caspian Sea.

The $6 billion development includes a new offshore platform and facilities designed to process up to 100,000 barrels of oil per day. The project is expected to achieve first production in 2023 and produce up to 300 million barrels over its lifetime.

The sanction is the first major investment decision by the ACG partnership since the extension of the ACG production sharing agreement (PSA) to 2049 was agreed in 2017. More than $36 billion has been invested into the development of the ACG area since the original PSA was signed in 1994.

Construction activities, which will commence this year and run through mid-2022, will take place in-country utilizing local resources. It is expected that, at peak, construction activities will create up to 8,000 jobs.

The Azeri Central East (ACE) project is centred on a new 48-slot production, drilling and quarters platform located mid-way between the existing Central Azeri and East Azeri platforms in a water depth of approximately 140 metres. The project will also include new infield pipelines to transfer oil and gas from the ACE platform to the existing ACG Phase 2 oil and gas export pipelines for transportation to the onshore Sangachal Terminal.

In addition, there will be a water injection pipeline installed between the East Azeri and ACE platforms to supply injection water from the Central Azeri compression and water injection platform to the ACE facilities.

ACG participating interests are: BP (30.37 per cent), SOCAR (25.0 per cent), Chevron (9.57 per cent), INPEX (9.31 per cent), Equinor (7.27 per cent), ExxonMobil (6.79 per cent), TPAO (5.73 per cent), ITOCHU (3.65 per cent), ONGC Videsh Limited (OVL) (2.31 per cent).